To be Established 1x30t/h high temperature, high pressure circulating fluidized bed boiler, 1x30MW condensing turbine & generator unit. Project is planned to be completed and put into operation at the end of 2013.
Circulating fluidized bed boiler: YG-130/9.8-M, 9.8MPa, 540 ℃, Jinan Boiler Group.
Turbine: N30-8.83, Qingdao Jieneng steam turbine group.
Generator: QF2W-30-2C, Jinan power equipment factory